EV CHARGER installation UK - WHY did we change the consumer unit?

2024 ж. 11 Мам.
48 951 Рет қаралды

All the customer wanted was an EV charger installed - so why did we decide to change the consumer unit?
In this video, we explore the process behind upgrading a consumer unit or fusebox to enable an EV charger to be installed.
Thanks to Ross from RS Electrix for helping to make this video. -
rselectrix.com/
🕐 TIME STAMPS 🕕
===============================
00:00 Changing a consumer unit for an EV charger installation.
00:26 Why are we changing the consumer unit.
01:21 Safe isolation procedure
01:47 Identify existing circuits
02:23 Adding a surge protection device
03:00 Removing the old Mk Sentry consumer unit
03:40 Moving consumer unit to gain more cable length
04:20 Preparing conductors for the new consumer unit.
05:05 Mounting new Schneider Easy 9 consumer unit
06:10 Wiring consumer unit
07:25 Re-connecting new 25mm meter tails
08:22 Setting torque to manufacturers instructions
09:00 Electrical installation testing
10:50 Re-plastering EV charger cable route
12:15 Electricians" what do you think?
================================
================================
Low-cost EV charging with Agile Octopus
hub.efixx.co.uk/octopus-energy
================================
More videos in this EV installation series
www.efixx.co.uk/ev-charger-ins...
================================
Are you an EV charger installer - check out these great services
EV Comply
Manage your installs, paperwork and win sales leads
hub.efixx.co.uk/EVcomply
Replenishh
Everything you need to install EV chargers and more!
hub.efixx.co.uk/replenishh
================================
📍SUBSCRIBE TO THE CHANNEL eFIXX helps electricians, electrical contractors, building services engineers, and electrical apprentices. Watching our videos, you'll discover new products, explore new applications and find answers to your technical questions. So if you've been on the tools for years or just starting your electrical journey, we'll help you stay up to date with the latest regulations and developments in the electrical industry.
hub.efixx.co.uk/youtube-subscr...
================================
📺 NEW TO THE EFIXX CHANNEL Watch our essential videos playlist hub.efixx.co.uk/essentials​
📺 CATCH UP ON THE LATEST VIDEOS
hub.efixx.co.uk/latest​
📺 ELECTRICIANS' TOOL REVIEW
hub.efixx.co.uk/tools​
================================
🔴 eFIXX LIVE Join us for our youtube live stream twice a month - features product sneak peeks, challenges, giveaways and live electrical banter.
NEXT STREAM HERE
👉hub.efixx.co.uk/next-live-stream​
Catch up on previous episodes
👉hub.efixx.co.uk/livestream​
================================
🆕 FREE CPD Learn about new applications, regulations and best practice with our FREE CPD modules. - New modules released every month covering everything from surge protection to lighting hub.efixx.co.uk/CPD​
================================
📝 APPRENTICE HUB If you're an electrical apprentice, retraining as an electrician or looking to refresh your knowledge, then please check out our apprentice hub. It contains thousands of multiple-choice questions to help prepare for electrical installation exams. hub.efixx.co.uk/apprentice​
================================
📩 eFIXX NEWSLETTER Sign up to find out about our live events, competitions and product giveaways.
www.efixx.co.uk/sign-up​
================================
FOLLOW US on your favourite social networks for behind the scenes action, breaking news and competitions.
🟠 INSTAGRAM hub.efixx.co.uk/Instagram​
🔵 LINKEDIN hub.efixx.co.uk/linkedin​
🟣 FACEBOOK hub.efixx.co.uk/facebook​
🟡TWITTER hub.efixx.co.uk/twitter​
==================================
❌ This content on this channel is for electrical professionals.❌ ==================================
📹 Presented by
Gary Hayers - Editor eFIXX
Gordon Routledge CEng MIET - Technology Editor eFIXX
===================================
#efixx #evcharging

Пікірлер
  • Loving the video! Just fitted my first 'three-phase' Schnider board as a first-year apprentice electrican. Discovered 'Ferruls' on a previous Efix video, haven't stoped using them in board installations. 👍🏻

    @callumbradley9265@callumbradley92652 жыл бұрын
  • If all dis board changes were as straightforward as this I would love going to work every day!

    @fernandez571@fernandez5712 жыл бұрын
  • Sounded like a couple of TV Cricketer Commentators when RS was doing the CCU.

    @elsdonsparks@elsdonsparks2 жыл бұрын
  • What I hate about the easy9 board, look how much space is below the RCBO’s.... yep, plenty, then above them it’s got hardly any space 🤷🏻‍♂️ Ross has done a belting job of that tho 👌🏼 well done matey

    @Cablesmith@Cablesmith2 жыл бұрын
    • I havent fitted one and i wont. As you say loads of wasted space also who designed it so the buzz bar to go around the Neutral terminal. I have worked on one of those and a cable i had put in temporarily got stripped by the hinge a blew.

      @paulspicer754@paulspicer7542 жыл бұрын
    • @@paulspicer754 definitely designed on paper and not for the installer

      @Cablesmith@Cablesmith2 жыл бұрын
  • Fantastic job! 🤝 thanks for sharing. Personally I love the Schneider gear especially their 3phase stuff 👍

    @ayresomemaintenance4627@ayresomemaintenance46272 жыл бұрын
  • Wow. Who would've thought a video about a consumer unit could be so interesting?! Fascinating insight, guys. Thank you.

    @medialegend@medialegend2 жыл бұрын
    • We do try - thanks 🙏

      @efixx@efixx2 жыл бұрын
    • @@efixx 😆

      @medialegend@medialegend2 жыл бұрын
  • Not sure why your didn’t do the CU install yourself. Made me chuckle though as it comes across as you two are a couple and you brought an electrician in to change the CU in your family home 🤣

    @AlHos@AlHos2 жыл бұрын
    • 😂😂😂

      @efixx@efixx2 жыл бұрын
    • 😆

      @Cleofizoid@Cleofizoid2 жыл бұрын
  • Great quality job 👌

    @mikebolt9753@mikebolt97532 жыл бұрын
  • I thought we were past the myth of heavy load near the main switch. The thick copper busbar takes care of that. How much resistance will a 20cm link bar, 2 x 7mm thick have from end to end? A resistance test less than 0.005 ohms? Schneider Easy is not a good choice of CU or larger RCBO's. The wylex, MK, fusebox CU have good space. Especially with Compact RCBO. The space above the breaker and behind the busbar is what sparkies want.

    @aadd3538@aadd35383 ай бұрын
  • Top job Ross 👍🏻

    @petercook4350@petercook4350 Жыл бұрын
  • Great job 👍

    @JohnSmith-ws7fq@JohnSmith-ws7fq2 жыл бұрын
    • Thanks

      @efixx@efixx2 жыл бұрын
  • Very nice, the cutters you work with are not available in my country, but they are the best protection for users, and the ground is very good, good luck to all

    @rachidelfakir4574@rachidelfakir4574 Жыл бұрын
  • I do like those Schneider Boards, the're a quality bit of kit, which real thought in it's design has gone into. A work of art on it's internal too. I would be proud to have it in my home.

    @brianwood5220@brianwood52202 жыл бұрын
  • Interesting and informative as well as well presented as usual. I had a customer send me pictures of there ev installation, then tailed into the Hensley to a single switch (fused). Only problem for me is there is no space left for a battery installation. There was a t&e running to the garage, just plain, and it's into the consumer unit. The evc is near the garage but I'm not sure what cable has been used. And was the first point installation. I've asked the customer if it can be fitted outside the house which happens to be behind the CU. Oddly he wants th t&e changed, which is ran under the garden. I've not seen the cu. But I would run a separate switch as the unit has everything in it. So I can wire from the main feed or the CU. But for time cost, small cu wins

    @guywhoknows@guywhoknows2 жыл бұрын
  • A very professional job

    @peterclark5242@peterclark52422 жыл бұрын
  • How long did this job genuinely take? It’s a great job by the way. There’s always the thought of wanting to do a very neat job & test to make sure all good. But also imagine doing this at a customers house in winter when it’s dark by 4pm

    @avfczoff@avfczoff Жыл бұрын
  • as all the cables came from above, could you not have moved the consumer higher out of the way?

    @pauladventure@pauladventure2 жыл бұрын
    • Remember there are recomendations on how high a consumer unit should be mounted, which happen to accord fairly closley with the required heights for functional switches. The board as shown looks as if it is on the limits.

      @supportgemelectrics8961@supportgemelectrics89612 жыл бұрын
  • In an ideal world !

    @johndavies4919@johndavies49192 жыл бұрын
  • Seems weird that they went to so much effort to put the incoming Line conductor on the right side of the main switch. Any reason ? I initially thought it might be to create a direct feed to the SPD from the main switch, but I assume the 20A MCB is the feed for the SPD. Also; minor observation, but it is good practice to put the "solid" sides of the crocodile clips together when nulling the leads. This avoids the possibility of a higher resistance in the hinge of the levered side of the clips.

    @geraldelwood9660@geraldelwood9660 Жыл бұрын
  • im just waiting for 10 years time to have a new invention of the earth bar to be put on the left side of the box, wow i can see the future of electronics already making me wish i wasnt born.

    @nejendary@nejendary3 ай бұрын
  • Habt ihr gut gemacht.

    @florianbayer2054@florianbayer20542 жыл бұрын
  • JEEESUS - I laughed when you said the old board looked messy - Haha, that looked like a work of art to me (not an electrician) - Phew, you guys earn this money, I'd be showing this to your customers just before you hand in a quote.

    @GHOOGLEMALE@GHOOGLEMALE2 жыл бұрын
  • You would have a field day in our home, it was built in 1979 and that box at @1.25 with all the seperate switches son for parts of the house...well its the original one still a big square metal plate with a row of black flick switches lol, outside in a cupboard we do have a new electric box thing with the screen on etc do you know if i wanted a ev charging point would it all need to be replaced? though i think we would maybe need a bigger main fuse or something

    @marklola12@marklola122 жыл бұрын
  • Not a big fan of the cover screw hole locations, especially the one above the neutral cables. Lovely install.

    @goaway9487@goaway94872 жыл бұрын
  • Nice job. Just a suggestion that isn’t feasible at all installations, but keeping switchgear above 450mm/below 1200mm in domestic properties for disabled access does include the switchgear in the consumer unit & while gaining the extra for a neater job, the move would create problems for wheelchair users.

    @jonathanrose456@jonathanrose4562 жыл бұрын
    • Doubt a wheelchairs going through there though.better no joints and a board a bit higher.

      @carlosjackal7624@carlosjackal76242 жыл бұрын
    • @@carlosjackal7624 Not for someone in a wheelchair

      @jonathanrose456@jonathanrose4562 жыл бұрын
  • Tidy board that... 👍🏼👍🏼

    @thewarr10r1@thewarr10r12 жыл бұрын
  • Wow that looks like a busy job

    @noname1st139@noname1st139 Жыл бұрын
  • 2010 called they want there RCBO's with earth fly leads back

    @reece77778@reece777782 жыл бұрын
  • Would of liked to see the cpcs doubled over in the earth bar

    @supersparks9466@supersparks94662 жыл бұрын
  • Are the Schneider rcbos double pole? Or has the zappi charger got double pole isolation built in? Good video. 👍

    @Bazza-tn5ck@Bazza-tn5ck2 жыл бұрын
    • The Zappi is one of the few chargers with full RCD function built in.

      @efixx@efixx2 жыл бұрын
  • Superbly done, don't you have to leave 20% of the board as reserves?

    @9plusinstalaciones@9plusinstalaciones2 жыл бұрын
    • That’s the biggest board Schneider make !

      @efixx@efixx2 жыл бұрын
    • @@efixx Well then if that is the case, leave them with no lighting circuits or EV Charger 😂😂😂😂😂

      @9plusinstalaciones@9plusinstalaciones2 жыл бұрын
  • I have just been quoted an add on consumer unit at £259.99 in my quote. There is a separate £180 labour charge too for the installation of the EV charger. I'm not sure about that price because units do not cost anywhere near that figure, especially if its just a smaller add on to my existing consumer unit. It would be good to get a rough idea in these videos as to what things cost. Otherwise great content as always I have learned a lot. In fact its this video that has made me question the quote!

    @duaplex1@duaplex12 жыл бұрын
    • Sounds cheap - check out this video where we discuss costs. kzhead.info/sun/acNwntmJfKN3nHk/bejne.html

      @efixx@efixx2 жыл бұрын
    • @@efixx Ah thank you!

      @duaplex1@duaplex12 жыл бұрын
    • That's a good price, adding testing digging, plastering, and time. It can be a lot of work. I charge £220 plus parts. So it should give you a good idea of balance.

      @guywhoknows@guywhoknows2 жыл бұрын
  • Moving the CU is ok if all the cables come down, bit of a tw@t if the ground floor socket circuits come up

    @waynio67@waynio672 жыл бұрын
    • You got to have some luck - one cable from below to a socket looked like a ring, but was a radial.

      @efixx@efixx2 жыл бұрын
  • Do you need to protect the meter tails if they’re travelling through a wall? If so how is this carried out? Thanks guys

    @avfczoff@avfczoff Жыл бұрын
  • That consumer unit looked quite full, I'm guessing that was the largest size for a single phase consumer unit by the look of it. Do you think in the future we could be going to 3 phase installations ( thinking of some countries in Europe) on large new build domestic housing estates with extra circuits like Ev chargers and other possible extra circuits in the next say 5-10 years? Or maybe Equipment will get more energy efficient?

    @paultipton743@paultipton7432 жыл бұрын
    • Western Power Distribution now fit three phase cables as standard to new and upgraded installations. (not that all of the builders choose to use it though)

      @efixx@efixx2 жыл бұрын
    • @@efixx ok, I've not been on a new build site for well over 10 years,interesting to know. Obviously installations like that would have to go in on ground works before hand and would depend on cost and knowledge to the builder like i think you were referring to

      @paultipton743@paultipton7432 жыл бұрын
    • They are the only DNO adopting this approach. Three phase appearing in the residential sector could need some “retraining” for quite a few folks. Plus more residential appropriate 3 phase boards.

      @efixx@efixx2 жыл бұрын
    • @@efixx Western Power are in the areas counties I work in. Bit of an old joke pre western power when Midlands electricity board were about. Electricity meter reader knocks on a house door " M.E.B" Home owner " i be alright M.E.B"!

      @paultipton743@paultipton7432 жыл бұрын
    • There's bigger single-phase CUs out there - I know Contactum do dual-row ones. Fitted one at my house 10+ years ago as I had the room, and has been useful when I've wanted to add circuits over the years. Future proof(ish).

      @donkmeister@donkmeister2 жыл бұрын
  • Please can you do a video of how he marks up the cables etc. I've seen people put little lines on individual conductors etc? I'm just learning and it still confuses me lol. thanks.

    @CommonInvesting@CommonInvesting2 жыл бұрын
    • Use a marker pen on the cables. You will or should have a plan /schematic/labels, or use common installation layout and run them on the same number you removed from (Count and write).

      @guywhoknows@guywhoknows2 жыл бұрын
  • I'm an American owner of an old house that has had 3 significant breaker panel upgrades over the course of a number of decades of remodelling. I'd prefer it if electricians would think more about how things will look 20-50 years in the future and not just how it looks today. Modern cables might last 100+ years, so if people would adopt a convention of leaving a neat loop of cable in a wall cavity for all new circuits then future panels wouldn't need to shift position. I can already imagine a future requirement of Arc fault breakers at some point in the UK. And some companies in the USA have introduced WiFi smart breakers that might catch on. Both could require new panels with different layouts. Needlessly cutting wires short to make the current panel look perfect should stop.

    @JasonEDragon@JasonEDragon2 жыл бұрын
    • Brilliant comment - Future proofing is a major issue especially with the changes in world with EV, PV a d battery storage. We think the regulations and codes need to reflect the need for future proofing as electricians can only respond to the current needs and operate in a competitive market.

      @efixx@efixx2 жыл бұрын
    • I tend to always run more than is needed in terms of cables. The problem you have is clients who want the best price, who are just thinking about the here and now. 10 years ago, no one was thinking of ev power and solar was just getting underway.

      @guywhoknows@guywhoknows2 жыл бұрын
    • There are already breakers available that combine AFDD, RCD and MCB functionality in a single width DIN unit. I believe Hagar have one with Bluetooth connectivity for diagnostic purposes as well. That will fit in exactly the same space. One concern with all these things is that the failure modes are now very complex, and there is now even a phone App for the Hagar units and it's also possible to update the firmware on the breaker. This is going the way of modern cars - full of electronics requiring specialist software. nb. those very neat wiring jobs are fine, but I wonder if some flexibility for the future has been lost.

      @TheEulerID@TheEulerID6 ай бұрын
  • Would have beer an idea to test before changing the board

    @stevelawrence7111@stevelawrence7111 Жыл бұрын
  • As the first circuit from the main switch is the EV charger which is protected by a mcb From your previous video on the installation of the EV charger, it can be seen that the EV charging unit as been installed in the garden / patio area which is out of the curtlidge of the house. From this the pvc/swa circuit should be protected by an RCBO.

    @thomasfriend6264@thomasfriend62642 жыл бұрын
    • It is protected by an RCBo

      @efixx@efixx2 жыл бұрын
    • @@efixx From the verbal coomentry and the cicuit id on the cardboard states that it is the first circuit from thd maib switch, which is clearly a mcb

      @thomasfriend6264@thomasfriend62642 жыл бұрын
    • From the verbal comnentry and the cicuit id written on the cardboard the EV is designated Circuit No 1 , being nearest the main switch. There is a mcb in circuit 1 and not the EV RCBO .

      @thomasfriend6264@thomasfriend62642 жыл бұрын
    • @@thomasfriend6264 EV is No2. The MCB in No 1 is for surge protector

      @jezzaandrews1940@jezzaandrews1940 Жыл бұрын
  • at 10:24: ? Is there any real difference between 'little' r2 and any other term using 'big' R - assuming it followed by the defining number, e.g. R2 ?

    @oldbutstillcurious3615@oldbutstillcurious36152 жыл бұрын
  • Hi Gaz and Gordon, I'm not an electrician, but an interested learner. just watched JW video on prescribed zones, within the video JW states all buried cables need rcd protection, it seems on the video and other videos the ev cable concealed without RCD protection to the cable. I understand the zappi has rcd protection but not the cable to it ?

    @miketv8718@miketv87182 жыл бұрын
    • You are correct - the EV in this video has an RCD in the consumer unit to protect the cable as it’s buried in the wall.

      @efixx@efixx2 жыл бұрын
    • @@efixx Thank you, quick response, so the RCD within the zappi protects the cable leading to the zappi ?

      @miketv8718@miketv87182 жыл бұрын
    • Sorry just checked the first MCB isn't connected.

      @miketv8718@miketv87182 жыл бұрын
    • @@efixx what about selectivity of the rcd is there any time delays?

      @NaydenSpirdonov@NaydenSpirdonov2 жыл бұрын
    • So if a 6mm cable clipped to the internal garage and the charger had a built in rcd would the charger circuit be ok of a mcb within the consumer unit, and the rest of the house circuits on individual rcbo’s and additional surge protection within the board? Or would you recommend having all circuits including EV charger off individual rcbo’s?

      @dyfedjones9194@dyfedjones91942 жыл бұрын
  • No room at the top of the rcbo’s why didn’t they make it with a din rail lower down. Neat job

    @jamesmoon5632@jamesmoon56322 жыл бұрын
    • 8:22 The DIN rail seems to bend excessively under pressure. It looks as flimsy as the old plastic consumer units.

      @westinthewest@westinthewest2 жыл бұрын
  • Looks good . Don't they make the smaller rcbo for this make of board .

    @johnwaby4321@johnwaby43212 жыл бұрын
    • Not atm

      @efixx@efixx2 жыл бұрын
  • Hi guys, great quality install, though I would not choose that low location for ccu for safety reasons, as well as it's packed which generates heat, then I would put a small 24v fan to cool it down. ( to reject the heat).

    @ramzg5402@ramzg54022 жыл бұрын
  • +efixx Given the location, and drywall and such a large hole being made in the in the wall anyway, did anybody consider installing a recessed consumer unit instead?

    @sbusweb@sbusweb2 жыл бұрын
    • We prefer flush fit boards but very few are fitted. It would be very difficult as a retrofit in this install as it’s a solid wall behind the drywall.

      @efixx@efixx2 жыл бұрын
  • Why don't the RCBOs use the DIN rail as the functional earth? Why cant we have boards with live and neutral bus bars? Not an electrical but I've never understood this!

    @edcooper2396@edcooper23962 жыл бұрын
    • Schneider do a board where there are no neutral tails and there is such a bar for the neutral, however those boards are too expensive for most, and I don't know if it's available in single phase, efixx showed it but it was a three phase board.

      @acelectricalsecurity@acelectricalsecurity2 жыл бұрын
    • This DIN rail does exist, but this board is old fashion

      @tommymack3210@tommymack32102 жыл бұрын
    • Schneider do s board like that. Buts it's ludicrously expensive, as are the rcbos to go in it at £100 each...

      @arcadia1701e@arcadia1701e2 жыл бұрын
  • Would have looked nicer if you'd put the stickers on the inside.

    @mikeselectricstuff@mikeselectricstuff2 жыл бұрын
    • Stickers are to be visible

      @dc-sd3gd@dc-sd3gd2 жыл бұрын
    • @@dc-sd3gd I don't think Mike was suggesting that the stickers should go inside the consumer unit enclosure. He probably meant inside the lid.

      @westinthewest@westinthewest2 жыл бұрын
    • Mostly see them left inside the box!

      @EdthePlumber@EdthePlumber2 жыл бұрын
  • Where have all the neutral cables come from in the main neutral bar? I had understood the rcbo tool the circuit neutral so just the fly lead to the bar

    @EdthePlumber@EdthePlumber2 жыл бұрын
    • They are the fly leads out to feed each individual Rcbo

      @efixx@efixx2 жыл бұрын
    • Where they blue sleeved over the white, the clip I’m thinking of is before he fitted the flu leads from the rcbos?

      @EdthePlumber@EdthePlumber2 жыл бұрын
    • Ignore me! It was the functional earth he’s was connecting after! In the white wires

      @EdthePlumber@EdthePlumber2 жыл бұрын
  • It’s a shame the opportunity was missed to install a recessed consumer unit given its location, other than that faultless.

    @andrewbetteridge5331@andrewbetteridge5331 Жыл бұрын
  • Tidy job, surprised you didn't leave any spare ways for future expansion. Is there a reason for this? Shame for someone to have to re-do all that work in the future if more ways are needed

    @GlynHudson@GlynHudson2 жыл бұрын
    • This is the biggest board in the Easy 9 range! - A few circuits are redundant atm - e.g The property has a gas hob, but is wired for electric. Debate about having smoke alarms on an individual circuit or combined with a lighting circuit. Does the door bell really a dedicated circuit for an 8 watt load?

      @efixx@efixx2 жыл бұрын
    • @@efixx it’s not a debate, BS 5839-6 requires domestic smoke alarms to be on a shared circuit, not dedicated.

      @bencrew4376@bencrew43762 жыл бұрын
    • @@bencrew4376 - You’d best phone the ECA and debate it with them as it’s not the advice they give to members - kzhead.info/sun/qcaKqpmHsYuDgpE/bejne.html

      @efixx@efixx2 жыл бұрын
    • @@efixx ok hands up, you can have both options as per 5839 6...I’m a designer and should know better 😂

      @bencrew4376@bencrew43762 жыл бұрын
  • ❤❤❤👍👍👍👍👍

    @ELECTRICLIFE4U@ELECTRICLIFE4U Жыл бұрын
  • As big as that board is, it's tight for space at the top. Unusual to leave so much space at the bottom. Also considering the amount of innovation Schneider have in some of their boards, they have functional earth's on the rcbos in this one, very strange.

    @acelectricalsecurity@acelectricalsecurity2 жыл бұрын
    • Better to have it accessible to reset Rcbos without having to get a set of steps... 👍🏼

      @thewarr10r1@thewarr10r12 жыл бұрын
    • @PETER WILSON Schneider themselves make a range without the earth tail and also without the neutral tail, so it's not just the cheaper brands and I think Hager devices don't have the earth tail any more.

      @acelectricalsecurity@acelectricalsecurity2 жыл бұрын
  • On the video you said the surge protector would protect the car. Wouldn’t an EV have its own surge protection on the cars BMS?

    @leighgillard2209@leighgillard22092 жыл бұрын
    • good question - needs exploring but the £850 charger doesn't so in our book an SPD is worth the investment.

      @efixx@efixx2 жыл бұрын
    • I'm sure that will vary from model to model, but don't forget that surge protectors using MOVs (and spark gaps, to some degree) are sacrificial. I'd rather replace a surge protector in my CU than in my car - I bet that's the cheaper option!

      @obd6HsN@obd6HsN2 жыл бұрын
  • A couple of things are not quite right, but a great job by RS.

    @peterconnollyconnolly4090@peterconnollyconnolly40902 жыл бұрын
    • Could you point them out please. Thanks.

      @markgilder9990@markgilder99902 жыл бұрын
    • @@markgilder9990 1. No spare ways for possible future expansion, 2. No fire retardant sealer in cable knockout entries. Regards P.

      @peterconnollyconnolly4090@peterconnollyconnolly40902 жыл бұрын
  • Why not install a larger unit for future expansions? This I dont understand about UK electrics, you only have 1-3 spare places when switching a consumer unit or even installing new.

    @tommymack3210@tommymack32102 жыл бұрын
    • because we have dumb regs that cause you to basically throw the fuse board away and start again every 10 years or so.

      @edcooper2396@edcooper23962 жыл бұрын
    • It's at the point now where your better off fitting a small 3 phase board with a single phasing kit fitted. Gives the internal space and ways needed.

      @arcadia1701e@arcadia1701e2 жыл бұрын
    • @@edcooper2396 what the hell. What a dumb and wastefull regulation

      @tommymack3210@tommymack32102 жыл бұрын
    • @ed cooper it’s good for business though

      @supersparks9466@supersparks94662 жыл бұрын
  • When I got my ev charger fitted I got a Matt-e device fitted. Luckily my meters and consumer unit are in my garage.

    @richardashton2432@richardashton2432 Жыл бұрын
  • Alan partridge 😂 Ps good interesting video thanks

    @davidplenderleith4176@davidplenderleith41762 жыл бұрын
    • 🤣👍🏻

      @efixx@efixx2 жыл бұрын
  • wow, that metrel is almost out of battery. I get nervous when Isee a color scen with a battery icon that low.

    @JasperJanssen@JasperJanssen Жыл бұрын
  • Can't believe this is a recent vid ! I thought it would say a year or so ago.. why that board ? Its awful ! Why those RCBOS they are massive and the earth leads ?? Extremely neat and great job done but the board has been max'd out on an upgrade.. all in all not the best in my opinion..

    @calvinhale2723@calvinhale27232 жыл бұрын
    • Sorry the boards not 'awful' each time their own but like others have said ... no space where its needed

      @calvinhale2723@calvinhale27232 жыл бұрын
  • Thoughts on the door bell transformer being of a different manufacturer, tho not attached to the bus bar it is nevertheless non compliant with 536.4.203

    @ishkebab@ishkebab2 жыл бұрын
    • @@edcooper2396 Not really an IET issue, it’s more the manufacturers/ BEAMA getting involved and the CU assembly not complying with the BSEN 61439 series by mixing manufacturers components

      @ishkebab@ishkebab2 жыл бұрын
  • Was the supply to the car charger on an RCBO? As it has an RCD within the charger does this still provided adequate discrimination

    @jamesemptage3605@jamesemptage36052 жыл бұрын
    • Extra RCD to protect the cable - video coming soon discussing discrimination.

      @efixx@efixx2 жыл бұрын
    • @@efixx It'd be "selectivity" if Gaz had written this reply.... along with "twin and CPC" 😁

      @obd6HsN@obd6HsN2 жыл бұрын
    • Mcb does not give Earth Leakage protection to the Circuit as it goes beyond the curtludge of the building

      @thomasfriend6264@thomasfriend62642 жыл бұрын
  • That would give me the fear my test meter being that low on battery

    @jacktissington@jacktissington2 жыл бұрын
  • MK is still available someone brought them out. Company called Circpro

    @mintsauce563@mintsauce5632 жыл бұрын
    • Really, they are owned by Honeywell

      @acelectricalsecurity@acelectricalsecurity2 жыл бұрын
    • They sold the rights to the name to Circpro who are buying from the chinese manufacturer who made them for MK. Not sure if the warranty etc flows over.

      @efixx@efixx2 жыл бұрын
  • 03:06 Top Tip! 💰💰😂

    @PersonGamma@PersonGamma2 жыл бұрын
    • Get paid bang on time 👍

      @efixx@efixx2 жыл бұрын
  • Plastic CU and AC type RCDs in it’s self is not a valid reason to change the CU . Also having a second CU for the EV charger being unsightly isn’t a valid reason to change the Existing CU .. HSE note , now on page 4 of BS7671 and has been updated and made clear, also consumer units in dwellings page 99 of the latest edition of the onsite guide. Nice job though, Fantastic video as always guy’s 👍

    @seandempsey7351@seandempsey73512 жыл бұрын
    • Customer didn’t want another box by the front door.

      @efixx@efixx2 жыл бұрын
    • @@efixx I understand that but Gaz made a point of saying that the CU is made off plastic and had AC type RCDs. My point was that should not be used as a reason to change the CU also Gordon said fitting an additional CU for the EV charger would be unsightly, what he should have said was the client doesn’t want an additional CU because it would look unsightly. Just an obsefasion on my part. But who am I to argue i’am just a humble spark who’s opinion means nothing. It was a nice clean install though, great video as always 👍👍

      @seandempsey7351@seandempsey73512 жыл бұрын
  • I don't get why these small units are installed in the UK, there is no room for upgrade and little space to work with.

    @Faddnn@Faddnn2 жыл бұрын
    • If you notice with anything in the UK, it's either just the right size or too small, it's ridiculous, that goes for our electrical stuff and even our kitchens, where we design them, that if you plug the appliance in it won't go far enough back, that's the poor design we have over here, if the people designing them head to fit them, then maybe things would change.

      @acelectricalsecurity@acelectricalsecurity2 жыл бұрын
    • @@edcooper2396 yeah I have in the past, fitted a 3 phase board in customers homes and used a conversion kit, loads more room.

      @acelectricalsecurity@acelectricalsecurity2 жыл бұрын
    • Eaton Memshield boards have loads of room. Havells do a range called PowerSafe which is identical to the old Memshield 2 range. These are superior to the more modern cheaper-looking Memshield 3. They are single phase boards which have a similar style to 3-phase boards.

      @westinthewest@westinthewest2 жыл бұрын
    • @anthony Charles should you be fitting sockets behind appliances? I never do

      @supersparks9466@supersparks94662 жыл бұрын
  • So easy on a newly built cardboard home, try doing it on a 200-year-old barn conversion overhead fed and with a looped supply, and unable to move the board to get more length......

    @8skellerns@8skellerns2 жыл бұрын
    • Sounds like a separate consumer unit for the EV

      @efixx@efixx2 жыл бұрын
    • @@efixx Western Power is having to put in a new temporary seperate supply, and come back and provide a seperate cable to each home on the loop of 3 homes, digging up the yards to bury the cables! Massive job.....

      @8skellerns@8skellerns2 жыл бұрын
  • Why would you mount a CU at mid-level?? It looks hideous, slip down the stairs and smash into the CU - perfect. Perfect height for small children to have a poke around as well - is it going to be protected in any way? Should have been put at high level but of course that is more difficult.

    @andrewstafford-jones4291@andrewstafford-jones42918 ай бұрын
    • Building regulation set the height 1200mm

      @efixx@efixx8 ай бұрын
  • Yes if it all was so easy.Some of these electricians are better suited to hair platting and extentions.Bet there's more money in it than making a consumer board look fancy.😂

    @iancoles1349@iancoles134921 күн бұрын
  • Hmmm, double earth cables under 1 screw.. that would not be up to code over here

    @TeQniX84@TeQniX84 Жыл бұрын
  • what happens if you have more than one car that needs charging i take it you have a car, your partner and your van how will this effect the load requirement for the house and some people have 4 cars two adults two teenagers what happens then. is all ok for one car/van. like to hear your comments please.

    @johncostello9388@johncostello93882 жыл бұрын
    • Load sharing / Shedding is the key - see our Easee video to get the idea kzhead.info/sun/mMOaeradbJScY2w/bejne.html

      @efixx@efixx2 жыл бұрын
  • Board looks a bit in the way where it is, why not take the opportunity to move it up even higher? Looks like you'd be bumping into it when going up the stairs. Also, I'm not a fan of stickers on the outside of boards unless required by law.

    @J4MB0@J4MB02 жыл бұрын
    • or, as per my comment, recessed unit...

      @sbusweb@sbusweb2 жыл бұрын
  • wonder how much the WHOLE cost was from start to finish..when you think you need to add that cost to the supposed low running costs of a ev car so would not be as low or as money saving i guess

    @marklola12@marklola122 жыл бұрын
    • and how many EV charger installs require upgrade work before the EV charger can be installed?

      @jeta1f35@jeta1f352 жыл бұрын
    • @@jeta1f35 ..and how many other areas need work before a CU can be signed off. I know that if I wanted an EV Charger I've about 1k of work that would need to happen to meet regulations. CU, undersized armours, probably some dodgy circuits, etc.

      @timearp8185@timearp81852 жыл бұрын
  • i would have wanted it fitted as high up the wall as possible. no need to have someone you poke about once a year being so prominent

    @AaronNesbitt@AaronNesbitt2 жыл бұрын
    • Building regs set the height

      @efixx@efixx2 жыл бұрын
  • Are you from south Africa

    @yurishnaicker5737@yurishnaicker57372 жыл бұрын
    • Don’t think do 💭

      @efixx@efixx2 жыл бұрын
  • Great job, great video. Only everyone on KZhead will now think they are "competent" lol 😆

    @dannyakqj101@dannyakqj1012 жыл бұрын
  • Am I the only person in the world that uses flexi tails as standard?

    @londontrada@londontrada2 жыл бұрын
    • No

      @supersparks9466@supersparks94662 жыл бұрын
    • No

      @markpowell1456@markpowell1456 Жыл бұрын
  • That cu is way to low children could draw on it or even worst open it up and turn of trip switches to important appliance.

    @adreenryan2901@adreenryan29012 жыл бұрын
    • Building regulations set the height of consumer units.

      @efixx@efixx2 жыл бұрын
    • @adreen Ryan I suggest you bring up your kids not to do such vandalism

      @supersparks9466@supersparks94662 жыл бұрын
  • I would have pulled the meter tails through the right hand side of the board. Using a Milwaukee cordless soldering iron to shrink the tubing isn't the safest way to do it - a heatgun would be better. I'd also avoid using insulating tape in the build as it degrades into a sticky mess over time (even 3M Temflex). Still a massively neat job - he obviously goes the extra distance and treats it like it's his own house.

    @ilovetitanium4136@ilovetitanium41362 жыл бұрын
  • Great vid as always... Bit of a whistley nose though 🤷🏻‍♂️

    @purdypebbles@purdypebbles2 жыл бұрын
    • The challenges of site work with regards noise and set up etc.

      @efixx@efixx2 жыл бұрын
  • It's highly unlikely that the vast majority of house would require one charger. More like 3 or 4, a his and hers + child and visitors? Going forward I would install a separate CU, minimum 4 ways. Or put a commercial one or two servicing the same amount of EV's. One is just not enough. In the case of multiple chargers synchronised usage would have to be used reduce power consumption.....needs some thought....

    @neil03051957@neil030519572 жыл бұрын
  • Look at those wood screws being removed using a flat head screwdriver 😂

    @woopdairitiz@woopdairitiz2 жыл бұрын
  • Change to make money. Simply a Henry Block on the tails from the meter, tails from the block to the existing consumer unit. The other block tails to a new breaker and protection just for the outdoor charger and an in-line isolation switch then on to the charger on the outside of the building. Easier to mount a current limiter on the EVC this way too

    @JohnSmith-bx8zb@JohnSmith-bx8zb2 жыл бұрын
    • So where do you locate the new EV consumer unit? - Customer wasn't keen to have another box on the wall in the hallway.

      @efixx@efixx2 жыл бұрын
    • @@efixx those with an electric cupboard it works fine

      @JohnSmith-bx8zb@JohnSmith-bx8zb2 жыл бұрын
  • Not many spare ways there.

    @niceguy235uk1@niceguy235uk12 жыл бұрын
  • Anything to make more work and more wages more profit as simple charging point for a car to us into a major upgrade what do you think it is a bloody space rocket

    @jimmorris5700@jimmorris57002 жыл бұрын
    • How would you have advised we do the job?

      @efixx@efixx2 жыл бұрын
    • @@efixx Well letting the cat out of the bag doesn’t cover it always talk about saving with a heat pump I want to hear electricity firms are putting in three phases it’s a new houses et cetera one for people one for the car and one for the house What size heat pump is expected I wonder in my small house and use 44 kW of gas a day as of now , the ave is 60kw So heat pump input 20k for output 60k lecky to match gas at 21p kw ( for how long 21p) .£4 a day x 200 days is adding £800 to the av £800 yearly bill NOT including car charging . And you are they are joking about how we got to change the consumer unit I will put any three-phase I will need all this talk about a con job by everybody in the country from government down to firms and small companies. Cause she will be laughing you can see a future of endless profits and lots of work because why because the government is making it mandatory so you’ve got a captive public forced to do all these things.

      @jimmorris5700@jimmorris57002 жыл бұрын
    • @@jimmorris5700 no reply to that one mate. I seen a bloke the other day doing ring continuity from a socket, he only had 1 cable in the board 🤣 it should all be done from the board

      @familymatters5422@familymatters54222 жыл бұрын
  • Looks like 5 hours he took there.

    @carlosjackal7624@carlosjackal76242 жыл бұрын
    • More like 7

      @efixx@efixx2 жыл бұрын
  • Why is electrical installation always rubbish in the UK? Come to Germany and learn how to do it properly and safely. This is how our Boards look 30 years ago. 😂

    @sentchen123@sentchen1232 жыл бұрын
  • I used to make really tidy jobs of my single and three phase boards nowadays I couldn't give a fuck

    @YGELLYPIKER@YGELLYPIKER2 жыл бұрын
    • Thanks for the brutal honesty

      @efixx@efixx2 жыл бұрын
KZhead